Not necessarily a licensed area though.
Be a big disappointment if it isn’t. Summerbees was effectively oversubscribed (ie full) every week and the club went to the trouble of relocating the bar to the containers outside the East Stand. If they see the new City Square as a “fanzone” it’ll have to have bars
 
Yeah I got that. They will have ways to close it off.
The holes have continuity systems around the perimeter which at present is hidden in a sealed box, the cover is removed and the Bars pulled out into the opening. Loose bars are then lapped onto the pull out bars and the hole filled with concrete. From a structural point of view this gives the slab full continuity, i.e as if the hole was never there