I thought the stand was going to be ready for December this year ?

That was the reported target, yes. 'End of the year'. January has been mentioned, mostly with thinking they might wait till the festive period is over to get people in.
 
That was the reported target, yes. 'End of the year'. January has been mentioned, mostly with thinking they might wait till the festive period is over to get people in.
January doesn't look likely to me, there is talk of using the last few games as test events with a full opening next season. Stand including back of house should be done for Mid March. Seats complete for mid November.

I still think the on the pitch performances dictate when it opens and what that physically looks like.
 
IMG_4526.jpeg

IMG_4520.jpeg

IMG_4521.jpeg

IMG_4522.jpeg

IMG_4523.jpeg

IMG-4524.jpg


IMG-4525.jpg
 
I'm surprised there isn't more seats in place by now. When did they start installing those "safe standing" seats at the end of the stand; 3 or 4 weeks ago, now? Very few seem to have been installed since.
 
I'm surprised there isn't more seats in place by now. When did they start installing those "safe standing" seats at the end of the stand; 3 or 4 weeks ago, now? Very few seem to have been installed since.
It is about 60% done and could be around 75% on sat.
 