Going to be very last minute finish for co op assume they will get it done some how tho
I was in there today lots to be done still doesn't look like it can be done but they seem confident the bulk will be. Think they've accepted now it won't be complete for opening but will be ready enough for the reduced capacities for the first few events. Think it'll be awhile yet till everything is finished
 
I was in there today lots to be done still doesn't look like it can be done but they seem confident the bulk will be. Think they've accepted now it won't be complete for opening but will be ready enough for the reduced capacities for the first few events. Think it'll be awhile yet till everything is finished
It will be months and months until it is fully finished. EOTs in place for the major subs until the back end of the year (and have been since 2023)
 
Have been on a couple of walk around today and going on more this week, I've joined the Co-Op Live team as one of their managers and whilst the venue will not be perfect for this weekend, and will be months of snagging and stuff but within 12 months it will be a spectacular venue, just like moving into a new house nothing is perfect straight away that's the way to see the venue... there are currently 1350 staff working on site at any one time 24hrs a day doing fit out, landscaping and everything.
 
Have been on a couple of walk around today and going on more this week, I've joined the Co-Op Live team as one of their managers and whilst the venue will not be perfect for this weekend, and will be months of snagging and stuff but within 12 months it will be a spectacular venue, just like moving into a new house nothing is perfect straight away that's the way to see the venue... there are currently 1350 staff working on site at any one time 24hrs a day doing fit out, landscaping and everything.
You allowed to take photos
 
Have been on a couple of walk around today and going on more this week, I've joined the Co-Op Live team as one of their managers and whilst the venue will not be perfect for this weekend, and will be months of snagging and stuff but within 12 months it will be a spectacular venue, just like moving into a new house nothing is perfect straight away that's the way to see the venue... there are currently 1350 staff working on site at any one time 24hrs a day doing fit out, landscaping and everything.

Good luck with the job there… hope it goes well.
 
Have been on a couple of walk around today and going on more this week, I've joined the Co-Op Live team as one of their managers and whilst the venue will not be perfect for this weekend, and will be months of snagging and stuff but within 12 months it will be a spectacular venue, just like moving into a new house nothing is perfect straight away that's the way to see the venue... there are currently 1350 staff working on site at any one time 24hrs a day doing fit out, landscaping and everything.
Sent you a PM
 
Have put elsewhere but thought it should also go on here. I heard yesterday from someone high up in MCC that they intend to reinstall the old railway loop line from Piccadilly over the Ardwick Viaduct curve and join up with the existing underused track that runs to the east of the new Tesla Garage. Tesla only has a five year lease. MCC and the City Football Group intend to install a new train station near the Tesla garage. MCC are in the process of buying / acquiring the bits of land they don't own to get the track reinstalled. I guess this is now happening as HS2 is not going into Piccadilly now. Will obviously take a few years but is clearly good news.
Couple of new bridges and a petrol strimmer, jobs a good-un

IMG_6340.jpegIMG_6339.jpeg
 
Forgot to post these.

Walk this way

PXL-20240413-160842363-MP-2.jpg


PXL-20240413-160901914-MP-2.jpg
 

Don't have an account? Register now and see fewer ads!

SIGN UP
Back
Top