Victoria Riverside, Manchester | Construction Update
Here are photos and updates from the site of Victoria Riverside in Manchester, latest update of December 2022.
According to updates from the developer (FEC UK): the concrete frames are progressing swiftly with Tower B close to completion. Tower A has reached level 11 and Tower C is at level 15.
Further key milestones have been reached across build this period, with the installation of the unitised façade commencing. The façade has now reached level 4 on Tower C and level 2 on Tower B, allowing for the scheduled internal fit-out to commence. The internal fit-out will include the creation of interior walls alongside elements of electrical, plumbing and mechanical engineering.
The construction schedule for 2023 forecasts completion of the concrete frames at Towers B & C, and the commencement of lift installation and fitting of the unitised façade to Tower A. Further progress on the internal apartment fit-outs can be made once the façade has been installed.
View attachment 65205
View attachment 65208
View attachment 65209
Cars are always getting broken into and nicked around thereI parked my car round there for years. Absolute dump it was.
I had a company car at the time. Had the exhaust stolen of it once from there. Pretty grim part of town. Will be very interesting to see how it ends up.Cars are always getting broken into and nicked around there
Surreal.
^^ Last pic - looks like a pic from the 1970's.Victoria Riverside - 37/26/18/6 stories - Red Bank - City Centre
View attachment 65204
CSI PROP - Linkedin
Victoria Riverside, Manchester | Construction Update
Here are photos and updates from the site of Victoria Riverside in Manchester, latest update of December 2022.
According to updates from the developer (FEC UK): the concrete frames are progressing swiftly with Tower B close to completion. Tower A has reached level 11 and Tower C is at level 15.
Further key milestones have been reached across build this period, with the installation of the unitised façade commencing. The façade has now reached level 4 on Tower C and level 2 on Tower B, allowing for the scheduled internal fit-out to commence. The internal fit-out will include the creation of interior walls alongside elements of electrical, plumbing and mechanical engineering.
The construction schedule for 2023 forecasts completion of the concrete frames at Towers B & C, and the commencement of lift installation and fitting of the unitised façade to Tower A. Further progress on the internal apartment fit-outs can be made once the façade has been installed.