Completion targets, as noted in public in April last year. Not seen any updates since.
• the Stand, Nov 25
• Office block/museum Nov 25
• Hotel, Apr/may 26
• city square, Aug/sep 26.
It was interesting they saw the office opening at roughly the same time as the stand. Probably because of the shop/museum element that links to the stand. But that is the element that is currently furthest behind (and has had some significant changes to), so I could see that running late.
The hotel was always planned almost a season later, and then the square and public areas etc, almost a full year after the stand.
Bear in mind also that those targets were noted in support of discharging a planning condition, so while available in the public domain for those that know where to look, they weren't exactly 'advertised' as such. I.e it wasn't a formal statement or press release, so they aren't really dates that would have any meaningful impact on anyone's reputation if they did slip. Unlike the co-op for example that had set opening dates and bookings.