Re: Etihad Campus, Stadium Development and Collar Site (cont
The info is from a document that was part of the planning application so doesn't confirm when the pitch-side seats will be done, just the relocation of services. The planning permission is valid for a numbers of years
Marvin said:Thanks Kramer.kramer said:Marvin said:What will happen at the Etihad between now and August? Foundations?
Do you think we'll notice anything different inside the ground when we return in August, other than maybe a big crane hovering overhead? The last row on the South Stand 2nd tier is going at some point
Its all in here https://dl.dropboxusercontent.com/u/23674406/Etihad Expansion Logistics1.pdf
Phase 1 – Enabling works
Site establishment, including removal of fencing to the rear of the South Stand and removal
of 2no. trees to allow access.
Undergrounds services relocations (from foot print of new stands subject to separate
planning application).
Phase 2 – Substructure works
Sub structure works (piling and foundations externally and internally)
Phase 3 – Advanced works (close season)
Deconstruction of legends lounge and other works at box level
Temporary propping and jacking to allow cutting back of existing roof
New Steelwork and concrete slab up to level one to form a protected route for the public
Installation of front row of columns for the new tier
Erection of the Tower Cranes
Relocation of pitch side services ready for additional seating
Phase 4 – Main Construction works
Super structure – New structural steel frame and metal decking slabs
Ground floor slab including drainage and service ducts
Inner bowl precast terracing
Roofing structure and coverings
External envelope
MEP installations
Internal fit out
Adjustment to the rear of the existing terrace
Formation of additional rows of seating pitch side
External works
Phase 5 - Completion works (Final close season)
Closed season works (existing roof removal and terrace completion)
Testing and Commissioning
I knew I had seen it somewhere.
Interesting to see that preliminary work on pitch-side seats starts soon
Some reports keep quoting just the two ends, and a stadium capacity of 60k, but looks like we are going up to 62k.
The info is from a document that was part of the planning application so doesn't confirm when the pitch-side seats will be done, just the relocation of services. The planning permission is valid for a numbers of years