Phase 1 – Enabling works
Site establishment, including removal of fencing to the rear of the South Stand and removal of 2no. trees to allow access.
Undergrounds services relocations (from foot print of new stands subject to separate
planning application).
Phase 2 – Substructure works
Sub structure works (piling and foundations externally and internally)
---------------------------------------------------------------------------------------------------------------------------------------
Phase 3 – Advanced works (close season)
Deconstruction of legends lounge and other works at box level
Temporary propping and jacking to allow cutting back of existing roof
New Steelwork and concrete slab up to level one to form a protected route for the public
Installation of front row of columns for the new tier
Erection of the Tower Cranes
Relocation of pitch side services ready for additional seating
Phase 4 – Main Construction works
Super structure – New structural steel frame and metal decking slabs
Ground floor slab including drainage and service ducts
Inner bowl precast terracing
Roofing structure and coverings
External envelope
MEP installations
Internal fit out
Adjustment to the rear of the existing terrace Formation of additional rows of seating pitch side
External works
Phase 5 - Completion works (Final close season)
Closed season works (existing roof removal and terrace completion)
Testing and Commissioning
<a class="postlink" href="http://www.publicaccess.manchester.gov.uk/associateddocs/selecteddoc.aspx?104315-ssi-0004.pdf" onclick="window.open(this.href);return false;">http://www.publicaccess.manchester.gov. ... i-0004.pdf</a>
Phase 1 – Enabling works
Site establishment, including removal of fencing to the rear of the South Stand and removal of 2no. trees to allow access.
Undergrounds services relocations (from foot print of new stands subject to separate
planning application).
Phase 2 – Substructure works
Sub structure works (piling and foundations externally and internally)
---------------------------------------------------------------------------------------------------------------------------------------
Phase 3 – Advanced works (close season)
Deconstruction of legends lounge and other works at box level
Temporary propping and jacking to allow cutting back of existing roof
New Steelwork and concrete slab up to level one to form a protected route for the public
Installation of front row of columns for the new tier
Erection of the Tower Cranes
Relocation of pitch side services ready for additional seating
Phase 4 – Main Construction works
Super structure – New structural steel frame and metal decking slabs
Ground floor slab including drainage and service ducts
Inner bowl precast terracing
Roofing structure and coverings
External envelope
MEP installations
Internal fit out
Adjustment to the rear of the existing terrace Formation of additional rows of seating pitch side
External works
Phase 5 - Completion works (Final close season)
Closed season works (existing roof removal and terrace completion)
Testing and Commissioning