North Stand Construction Discussion

Could you tell me with all the work going on can you enter entrance C from the metro stop without the need of walking all round the stadium (Ashton road).
 
For those that take photos in passing or at games, keep an eye out for the facade bay mock-up over the next couple of weeks.

They were programmed in by Sisk for the next two weeks, to be put up for agreement with planners. If that hasn't slipped.
Sorry for being an ignoramus Coatigan but what is this 'facade bay mock-up' you speak of? Asking for a friend.
; )
 
Sorry for being an ignoramus Coatigan but what is this 'facade bay mock-up' you speak of? Asking for a friend.
; )
They will install a 1:1 partial bay of the facade, for the planners to agree the final material finish colour and junction detail, in the arrangement as below.

1000014071.jpg


It is part of the approval conditions, it was initially set for prior to works starting, but they have managed to agreee to defer it to mid april, to allow steelwork to progress and the procurement to happen. Also gives a frame on site to fix it to, as opposed to having to make one up for it.
 
They will install a 1:1 partial bay of the facade, for the planners to agree the final material finish colour and junction detail, in the arrangement as below.

View attachment 112699


It is part of the approval conditions, it was initially set for prior to works starting, but they have managed to agreee to defer it to mid april, to allow steelwork to progress and the procurement to happen. Also gives a frame on site to fix it to, as opposed to having to make one up for it.
Thanks for the clarification. Very interesting (in spite of some recent whinging from certain quarters).
I'm curious. Where such a mock-up is planned in to a build, does it allow for significant changes to design, material, finish etc or are we too far down the track? As said, I'm speaking very much as a layman!
 
Thanks for the clarification. Very interesting (in spite of some recent whinging from certain quarters).
I'm curious. Where such a mock-up is planned in to a build, does it allow for significant changes to design, material, finish etc or are we too far down the track? As said, I'm speaking very much as a layman!

It should, that's kind of the whole point. It gives the planners (or indeed the club as a client who would be seeing it for the first time too in the flesh) a chance to make comments or requests, and tweaks. And that does sometimes happen.

Once it is agreed and signed off, it gives the contractor comfort to finalise the orders (almost said financials there lol). And at that point, it is then somewhat a case of too far down the line. There are still mechanisms to change things, but that would be rare, and for unforseen reasons like supply chain issues, subbies going bust etc, rather than by choice if that makes sense.

Sometimes it can be a basic tickbox excersise, sometimes it can become contentious and lead to changes. All depends really, on the actual finish, its percieved importance, and mostly who happens to be dealing with it. But either way, the wider public get to see it as a glimpse of what it all will look like.
 
Last edited:
Thanks for the clarification. Very interesting (in spite of some recent whinging from certain quarters).
I'm curious. Where such a mock-up is planned in to a build, does it allow for significant changes to design, material, finish etc or are we too far down the track? As said, I'm speaking very much as a layman!

Here is a good example of one, from elsewhere, that @jrb previously posted on another thread. Shows all the key materials and colours against each other for reference and in real life/light.

It gives the planners or client the chance to go, fuck me that pink is too pink, or that bronze is too yellow etc, and change it, before it is on all of it. Should they wish to of course.

1000014072.jpg

Our one will be in the arrangement in the earleir post.
 
They will install a 1:1 partial bay of the facade, for the planners to agree the final material finish colour and junction detail, in the arrangement as below.

View attachment 112699


It is part of the approval conditions, it was initially set for prior to works starting, but they have managed to agreee to defer it to mid april, to allow steelwork to progress and the procurement to happen. Also gives a frame on site to fix it to, as opposed to having to make one up for it.
Does this mean a bigger sail than the fin @Coatigan

1712239591729.png
 

Don't have an account? Register now and see fewer ads!

SIGN UP
Back
Top
  AdBlock Detected
Bluemoon relies on advertising to pay our hosting fees. Please support the site by disabling your ad blocking software to help keep the forum sustainable. Thanks.