He stadium might look complete but teething issues and doing all the snagging in a building of that size and complexity would I should imagine take ages. Then there will be a huge ammount of testing of services to conduct. Fire systems, sprinkler, electrical circuits, drainage, alarms, plumbing, cctv, PA, computer systems. You name it, it's probably all in that stadium all needing approval, then there will need to be staff training which all takes time and scrutiny will no doubt be tight after Grenfell. These things take months on a building that size not a couple of weeks.
Correct and why I said Levy been new all this and has strung the fa along with his lies.