PROJECT UPDATE: One Victoria, Manchester
Maintaining a focus on project completion has helped our team at One Victoria, Manchester, achieve a significant milestone: both Blocks A and B are about to reach topping out.
Block A reinforced concrete frame has progressed to level 10, with parapet walls being formed. Block B reinforced concrete frame to level 10 was completed at the beginning of April.
The ground floor blockwork is 50% complete on both blocks, including the car park, water tank room, and LV room on Block B.
The focus over the next 6 weeks will be completing the substation at Block A.
While topping out blocks A and B is visible to everyone, much work has been going on behind the scenes. Internal first fix MEP, soil vent pipes, rainwater downpipes, and ducting are now complete.
Block B is now progressing with frames and glazing installed up to level 4, SFS steel and cement board up to level 6, and frames and glazing installed up to level 4.
Safe access has also been installed, commissioned and in use, including that for Great Ducie Street and Breslynn Street.
Great to see lots of progress on this new 129 residential apartment development in the heart of Manchester for our client One Heritage Group PLC.